No. 78-1185.United States Court of Appeals, Third Circuit.Argued October 6, 1978.
Decided December 8, 1978. As Amended February 8, 1979.
Page 143
James B. Liberman, Leonard W. Belter, Donald K. Dankner, Debevoise Liberman, Washington, D.C., for petitioner.
Robert R. Nordhaus, Gen. Counsel, Howard E. Shapiro, Sol., Lynn N. Hargis, Atty., Washington, D.C., for respondent, Federal Energy Regulatory Commission.
William C. Wise, Robert Weinberg, Washington, D.C., for intervenor, Allegheny Electric Cooperative, Inc.
William I. Harkaway, Belnap, McCarthy, Spencer, Sweeney
Harkaway, Washington, D.C., for intervenors, Boroughs of Madison, Butler, Lavallette, and Seaside Heights, N. J.
Petition for review from the Federal Energy Regulatory Commission.
Before ROSENN and WEIS, Circuit Judges and HANNUM, District Judge.[*]
[1] OPINION OF THE COURT
WEIS, Circuit Judge.
Page 144
The clause became effective on December 2, 1973, and read in pertinent part:
[4] There followed a formula that included as factors the cost of fuel and sales in current and base periods, taxes, and a component for adjustment of losses to the delivery voltage. In defining current sales and fuel costs, the tariff stated that these “factors are to be determined as the three month totals for the period ending with the second calendar month preceding the billing month.” [5] With some revisions not material here, Jersey Central billed its customers under the new arrangement until July 27, 1976, when the company filed a proposed new schedule of wholesale electric rates, including a three-step increase in the base cost component of the fuel adjustment clause. This phase-in mechanism[3] was designed to recover “unbilled fuel costs” still owed by customers, according to the utility, under the superseded adjustment clause. The contention was that such a device, similar in effect to temporary surcharges, was needed to recoup fuel costs already incurred. Because the original fuel adjustment charge was based on a time period ending two months before the billing date, the company asserted that a billing lag had resulted. [6] The boroughs of Lavallette, Madison, Butler, and Seaside Heights, and Allegheny Electric Cooperative, Inc., wholesale customers of Jersey Central, intervened and urged rejection of the proposed fuel adjustment clause as an attempt to retroactively recover fuel costs which the original clause had failed to include. Subsequently, the customers sought severance and summary disposition of the phase-in question in light o Public Service Co. of New Hampshire, Opinion Nos. 790 and 790-A, FERC Docket ER76-285 (1977), petition for review filed,“An energy cost adjustment factor shall be applied to each kilowatt-hour supplied under this tariff. This energy cost adjustment determined . . . in accordance with the formula set forth below, shall be applied to all kilowatt-hours supplied during the billing month.”
Page 145
[8] The Commission, however, takes the position that the 1973 tariff did no more than establish a formula, based on past experience, i.e., costs incurred during a prior test period, to compute what was in effect an approximation of the excess and still unknown fuel costs for the billable month. It insists that the company did receive the proceeds of the fuel adjustment charge for every month it had been in effect. Under this view, once Jersey Central had collected its adjustment charge for a particular month, the company had assessed all it was entitled to collect, and there were no unbilled fuel costs still owed by the customer. The Commission contends that because the adjustment rate may have been inadequate to some extent in recapturing costs is not justification for a retroactive charge. Its position is that there was no billing lag and therefore no basis for the phase-in procedure. [9] The legality of the 1976 clause therefore hinges on the one adopted in 1973. Since the dispute centers on the interpretation of the 1973 tariff, the appropriate place to begin is with its wording, bearing in mind the construction should be that reasonably communicated to those governed by it, and any doubt as to the meaning should be resolved against the filing utility Cf. United States v. Missouri-Kansas-Texas Railroad, 194 F.2d 777Page 146
energy cost incurred during a billable month. It was not absolutely accurate, it did not exactly charge each customer with his proportionate share of expense incurred, at least in the beginning, but it did offer a reasonable basis for estimation.[4]
[14] Two cases involving similar fuel adjustment clauses have been reviewed by the Courts of Appeals for the First and the Fourth Circuits. In Virginia Electric Power Co. v. Federal Energy Regulatory Commission, 580 F.2d 710 (4th Cir. 1978), the Fourth Circuit, in agreement with our view, took the position that the fuel adjustment clause did not provide for recovery of past excess fuel costs but represented the orthodox use of a test period to arrive at current costs. The First Circuit took a somewhat different approach in Maine Public Service Co. v. Federal Power Commission, 579 F.2d 659 (1st Cir. 1978). There, the court felt that the Commission had taken an unduly narrow view of the “filed rate doctrine”[5] based on the Commission’s misreading of Montana-Dakota Utilities Co. v. Northwestern Public Service Co., 341 U.S. 246, 71 S.Ct. 692, 95 L.Ed. 912 (1951). Believing that there was error in the Commission’s reliance on Montana-Dakota as support for its conclusion that it lacked legal authority to allow a surcharge, the court remanded the Maine case for further consideration. [15] We have carefully reviewed the Commission’s opinion in New Hampshire, the seminal decision in the fuel adjustment clause cases, and with due respect to the Court of Appeals for the First Circuit, we do not agree that the agency’s ruling there rises or falls on its interpretation of Montana-Dakota. Rather, the thrust of the New Hampshire case is the construction of the tariff itself. Regardless of whether Montana-Dakota forecloses the phase-in here, it appears to us that the Commission is on solid ground in concluding that a reasonable interpretation of the tariff compels the result it reached. [16] There may be sound reasons to question a general indiscriminate reliance upon administrative expertise but we think it proper to extend some deference to the Commission’s interpretation of tariffs, a specialized area in which the agency undoubtedly has extensive experience. In any event, the Commission’s construction in this case coincides with our own view. See, e. g., Associated Press v. FCC, 146 U.S.App. D.C. 361, 366-67, 452 F.2d 1290, 1295-96 (D.C.Cir. 1971). [17] The company argues that questions of fact remain and that it was therefore improper for the Commission to utilize summary disposition in these circumstances. We have examined the company’s position on disputed factual issues but conclude that the interpretation of the tariff in this case is a matter of law which would be unaffected by the company’s proffered evidence. [18] We point out that the issue under consideration here goes only to the rejection of the phase-in mechanism of the fuel adjustment clause. That question was servered from the proceeding for consideration of whether the entire clause was just and reasonable. Thus, in no way has the Commission nor have we passed on the question whether the clause interpreted as a current charge based on past data is just and reasonable. [19] The order of the Commission will be affirmed.Under Jersey Central’s fuel clauses, actual costs for a three-month period ending two months prior to the billing month are determined on a per kilowatt-hour basis. These costs are indexed against a base cost per kilowatt-hour. The difference is then expressed as a “factor” which increases — or decreases — in cents per kilowatt-hour the charge for each kilowatt-hour sold in a billing month.
Page 147
142 F.2d 820 (1944) SPENCER et al. v. MADSEN. SAME v. HEYNE SERVICE STATION, Inc.…
PRECEDENTIAL UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________ No. 17-1434 _____________ ANTHONY…
PRECEDENTIAL UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________ No. 17-1588 _____________ COLLEEN…
PRECEDENTIAL UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________ Nos. 16-3816 & 17-1705…
860 F.3d 111 (2017) Jeffrey M. NORMAN, Appellant in No. 16-1924 v. David W. ELKIN;…
PRECEDENTIAL UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________ Nos. 14-4237, 15-1247, 15-3433…