No. 88-5112.United States Court of Appeals, Third Circuit.Argued May 3, 1988.
Decided May 24, 1988.
Michael S. Waters (argued), Lois H. Goodman, Carpenter, Bennett Morrissey, Newark, N.J., Burton L. Ansell, General Motors Corp., Detroit, Mich., for appellant.
Nicholas L. Ribis (argued), Bruce R. Volpe, James J. O’Hara, Ruth M. Meyer, Ribis, Graham, Verdon Curtin, Morristown, N.J., for appellee.
Appeal from the United States District Court for the District of New Jersey.
Before GIBBONS, Chief Judge, and MANSMANN and COWEN, Circuit Judges.
Page 101
[1] OPINION OF THE COURT
COWEN, Circuit Judge.
I.
[3] Frank’s GMC has been a GM franchisee since 1937, and has sold the full line[1] of GM trucks since 1973. In October 1986, GM informed Frank’s GMC that it had formed a joint venture with A.B. Volvo, known as Heavy Truck Corporation (“Volvo/GM”) (in which GM was to be a minority participant) to manufacture and market heavy-duty trucks in North America. As a consequence of the joint venture, GM also advised Frank’s GMC that it was no longer going to manufacture and supply them with heavy-duty trucks and parts. Nevertheless, Frank’s GMC anticipated receiving heavy-duty trucks from the joint venture because of its past superior sales record with GM. However, in July of 1987 Volvo/GM informed Frank’s GMC that it would not be selected to market and service these trucks on behalf of the joint venture. In addition, Frank’s GMC was informed that it should cease taking orders for GM heavy-duty trucks and that orders for heavy-duty truck parts would be considered on a case-by-case basis.
II.
[6] “We have consistently held that our review of the grant or denial of preliminary injunctions is limited to determining whether there has been an abuse of discretion, an error of law, or a clear mistake in the consideration of the proof.” Moteles v. University of Pennsylvania, 730 F.2d 913, 918 (3d Cir.) cert. denied, 469 U.S. 855, 105 S.Ct. 179, 83 L.Ed.2d 114 (1984); see also Marxe v. Jackson, 833 F.2d 1121, 1125 (3d Cir. 1987); Morton v. Beyer, 822 F.2d 364, 367 (3d Cir. 1987). Our scope of review is narrow because “the grant or denial of a preliminary injunction is almost always based on an abbreviated set of facts, requiring
Page 102
a delicate balancing . . . [that] is the responsibility of the district judge. . . .” United States Steel Corp. v. Fraternal Ass’n of Steelhaulers, 431 F.2d 1046, 1048 (3d Cir. 1970) Marxe, 833 F.2d at 1125.
[7] We have recognized many times that the grant of injunctive relief is an extraordinary remedy, United States v. City of Philadelphia, 644 F.2d 187, 191 n. 1 (3d Cir. 1980), which should be granted only in limited circumstances. To obtain this ad interim relief, a movant “must demonstrate both a likelihood of success on the merits and the probability of irreparable harm if relief is not granted.” Morton, 822 F.2d at 367. “[W]e cannot sustain a preliminary injunction . . . where either or both of these prerequisites are absent.” In re Arthur Treacher’s Franchisee Litig., 689 F.2d 1137, 1143 (3d Cir. 1982); Morton,822 F.2d at 367.
A.
[8] In this case, it is clear to us that there is an insufficient basis upon which a finding of irreparable injury can be made to support the district court’s order compelling GM to provide parts and warranty support.[2] The assertions of Frank’s GMC, even if true, do not constitute irreparable harm.[3]
Page 103
and adduce proof of actual or imminent harm which cannot otherwise be compensated by money damages, it has failed to sustain its substantial burden of showing irreparable harm. The district court, thus, erred in granting the injunction.
B.
[12] We also recognize, however, an additional independent basis for reversal. The district court failed to require Frank’s GMC, as a successful applicant, to post a bond. This failure is in direct conflict with Rule 65(c) of the Federal Rules of Civil Procedure, which mandates that a court when issuing an injunction must require the successful applicant to post adequate security.[5]
Although the amount of the bond is left to the discretion of the court, the posting requirement is much less discretionary. While there are exceptions, the instances in which a bond may not be required are so rare that the requirement is almost mandatory. We have held previously that absent circumstances where there is no risk of monetary loss to the defendant, the failure of a district court to require a successful applicant to post a bond constitutes reversible error. System Operations, Inc. v. Scientific Games Dev. Corp., 555 F.2d 1131, 1145-46 (3d Cir. 1977).[6] Here, there was evidence in the record indicating that GM would incur substantial costs in complying with the terms of the injunction.[7] Indeed, the district court recognized that “although harm would occur to GM if the preliminary injunction was continued and not stayed or dissolved . . . it is not irreparable, and pales in significance to the potential loss of Plaintiff.” App. at 290. Given the clear possibility that GM could be forced to incur costs with no way to seek restitution if Frank’s GMC does not prevail, it was error for the court below to deny GM’s request for a bond.
III.
[13] We conclude that Frank’s GMC did not meet its affirmative burden of showing irreparable injury. Therefore, the district court improvidently granted ad interim relief. Furthermore, the district court erred in issuing the injunction without requiring Frank’s GMC to post a bond. For the foregoing reasons, we will reverse and remand with instructions to vacate the preliminary injunction.
(c) Security. No restraining order or preliminary injunction shall issue except upon the giving of security by the applicant, in such sum as the court deems proper, for the payment of such costs and damages as may be incurred or suffered by any party who is found to have been wrongfully enjoined or restrained.
Fed.R.Civ.P. 65(c). The reason for this requirement is simple: The party against whom an injunction is issued has no legal or equitable means to recover against the applicant for a wrongful grant of the injunction (i.e., where the applicant does not prevail in the main action), other than the bond.
Frank’s GMC argues that any damages incurred by GM are purely of its own making because GM has made the choice to dismantle its warranty support and sell off or transfer its parts inventory. However, this argument is spurious as GM would incur costs in complying with the injunction whether it phased parts and warranty services out and had to reconstitute them, or whether GM itself continued to maintain them.
Page 104